Case Reports
All contributions regarding the following information are gratefully accepted and should be directed to Lisa Donohoe (Editor)
In this case (for which leave has been given to appeal to the High Court), the NSW Court of Appeal made a declaration that an expert determination was not binding on the parties. MacFarlan J, in the principal judgment, reasoned that, there being an inconsistency in the reasoning of the expert, in making the determination he had made, and determining that the Principal had, in making variations, delayed completion, thereby entitling the Contractor to an extension of time, yet failing to give the Contractor delay costs: “the Contractor can fairly say, as it does, that it has not been told by the Expert why it is not entitled to delay costs”. Macfarlan J concluded that, the expert, in failing to give reasons, had gone outside the expert determination agreement, accordingly: “A departure from the Contract having been demonstrated by the Contractor, the whole of the Expert Determination must therefore be regarded as being outside the contemplation of the Contract. The Contractor is thus entitled to a declaration that the Expert Determination is not binding upon the parties to these proceedings.”
Other Recent Entries
- Altain Khuder LLC v IMC Mining Inc & IMC Mining Solutions Pty Ltd [2011] VSC 1
- Thomas v Powercor Australia Limited (Ruling No 1) [2010] VSC 489 (29 October 2010)…
- Chase Oyster Bar v Hamo Industries [2010] NSWCA 190
- Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2010] NSWCA 59 (19 Ap…
- Roads Corporation v Love [2010] VSC 253 (Vickery J)
- Anderson Formrite Pty Ltd v Baulderstone Pty Ltd (No 7) [2010] FCA 921
- View all Case Reports Updates

