Case Reports
All contributions regarding the following information are gratefully accepted and should be directed to Angela Vaccari (Editor)
In BMD Major Projects Pty Ltd v Victorian Urban Development Authority [2009] VSCA 221 (7 October 2009), the Victorian Court of Appeal considered whether a Contractor was entitled to recover extra payment for work to deal with latent conditions different from those which the contractor should reasonably have contemplated. The Appellant claimed that the respondent did not give adequate notice of latent conditions based on delay and that the latent conditions were exacerbated by unexplained delay of respondent. Held: i) adequate notice given as delay short and area needed to be properly surveyed before material change in physical conditions became apparent; ii) VSC did not err in invoking estoppel as respondent's pleading and particulars sufficiently wide enough to justify decision; and iii) Appeal allowed due to VSC error in applying rate for additional wet based treatment and value of delay caused by latent conditions.
Other Recent Entries
- Role of architect proprietors when administering a building contract
- Damages for defective work - relevance of plaintiff's future intention
- Court of Appeal considers meaning of “building work” and “building action”…
- High Court rules on whether loss of chance should be extended to medical negligenc…
- Consequential loss - What's in and what's out?
- What amounts to a deed and when is “a deal a deal”?
- View all Case Reports Updates

