Case Reports
All contributions regarding the following information are gratefully accepted and should be directed to Lisa Donohoe (Editor)
In BMD Major Projects Pty Ltd v Victorian Urban Development Authority [2009] VSCA 221 (7 October 2009), the Victorian Court of Appeal considered whether a Contractor was entitled to recover extra payment for work to deal with latent conditions different from those which the contractor should reasonably have contemplated. The Appellant claimed that the respondent did not give adequate notice of latent conditions based on delay and that the latent conditions were exacerbated by unexplained delay of respondent. Held: i) adequate notice given as delay short and area needed to be properly surveyed before material change in physical conditions became apparent; ii) VSC did not err in invoking estoppel as respondent's pleading and particulars sufficiently wide enough to justify decision; and iii) Appeal allowed due to VSC error in applying rate for additional wet based treatment and value of delay caused by latent conditions.
Other Recent Entries
- Altain Khuder LLC v IMC Mining Inc & IMC Mining Solutions Pty Ltd [2011] VSC 1
- Thomas v Powercor Australia Limited (Ruling No 1) [2010] VSC 489 (29 October 2010)…
- Chase Oyster Bar v Hamo Industries [2010] NSWCA 190
- Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2010] NSWCA 59 (19 Ap…
- Roads Corporation v Love [2010] VSC 253 (Vickery J)
- Anderson Formrite Pty Ltd v Baulderstone Pty Ltd (No 7) [2010] FCA 921
- View all Case Reports Updates

