Case Reports
All contributions regarding the following information are gratefully accepted and should be directed to Angela Vaccari (Editor)
In Bruton Pty Ltd, M. v NSW Land & Housing Corp & Anor [2009] NSWSC 1431 (11 December 2009), the New South Wales Supreme Court considered an application for interlocutory injunction to retrain the Respondent calling upon a guarantee to compensate cost of rectifying defects and losses arising from late completion. The building contract required Applicant to provide bank guarantee as security of performance. Respondent claimed breach of contract because defects in building work and construction completed outside time stipulated, making allowance for extensions. Applicant claimed no material breach of contract. Held: Application granted. Balance of convenience favoured injunction because Applicant would incur financial difficulties whereas Respondent would not suffer any hardship and would still have security of bank guarantee.
Other Recent Entries
- Role of architect proprietors when administering a building contract
- Damages for defective work - relevance of plaintiff's future intention
- Court of Appeal considers meaning of “building work” and “building action”…
- High Court rules on whether loss of chance should be extended to medical negligenc…
- Consequential loss - What's in and what's out?
- What amounts to a deed and when is “a deal a deal”?
- View all Case Reports Updates

