Case Reports
All contributions regarding the following information are gratefully accepted and should be directed to Lisa Donohoe (Editor)
In Bruton Pty Ltd, M. v NSW Land & Housing Corp & Anor [2009] NSWSC 1431 (11 December 2009), the New South Wales Supreme Court considered an application for interlocutory injunction to retrain the Respondent calling upon a guarantee to compensate cost of rectifying defects and losses arising from late completion. The building contract required Applicant to provide bank guarantee as security of performance. Respondent claimed breach of contract because defects in building work and construction completed outside time stipulated, making allowance for extensions. Applicant claimed no material breach of contract. Held: Application granted. Balance of convenience favoured injunction because Applicant would incur financial difficulties whereas Respondent would not suffer any hardship and would still have security of bank guarantee.
Other Recent Entries
- Altain Khuder LLC v IMC Mining Inc & IMC Mining Solutions Pty Ltd [2011] VSC 1
- Thomas v Powercor Australia Limited (Ruling No 1) [2010] VSC 489 (29 October 2010)…
- Chase Oyster Bar v Hamo Industries [2010] NSWCA 190
- Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2010] NSWCA 59 (19 Ap…
- Roads Corporation v Love [2010] VSC 253 (Vickery J)
- Anderson Formrite Pty Ltd v Baulderstone Pty Ltd (No 7) [2010] FCA 921
- View all Case Reports Updates

